Indonesia 300-Person Mining Camp Project

Project Overview
Location: coal mine site, Kalimantan Island, Indonesia

Year: 2022
Capacity: 300-person camp, 294 beds
Product: quick-assembly Detachable container house 
Quantity: 213 container units across 19 buildings
Shipping: 17 × 40HQ containers
Production: 18 days
Transport: 15 days
On-site installation: 30 days
Scope: staff dormitories, senior staff quarters, guest house, administration block, clinic, laundry, two canteens, warehouse and site inspection post
Set Inquiry
Categories
Categories

How 213 Quick-Assembly Units Built a 294-Bed Mine Camp in Kalimantan

A 294-bed workforce camp for a coal mine in Kalimantan, delivered from 213 quick-assembly container units. 18 days in production, 17 x 40HQ shipped, 30 days on site — including reinforced packing for a multi-leg route and raised bathroom platforms for drainage.
How 213 Quick-Assembly Units Built a 294-Bed Mine Camp in Kalimantan,9STATES MODULAR BUILDING SHANGHAI CO., LTD.
Case Details

294 Beds on a Coal Mine in Kalimantan:
213 Quick-Assembly Detachable Container House Units, 63 Days From Factory to Handover

Coal projects on Kalimantan do not sit near anything. The mine is inland, the port is hours away, and the road between them changes condition with every rainy season. Camps have to be standing before the workforce arrives, which leaves very little room for a construction method that depends on dry weather and a stable local labour pool.

That is the case for factory-built accommodation. When the building is manufactured indoors and the site only has to assemble it, the weather stops setting the schedule. This project — 213 quick-assembly container units forming a 294-bed camp for a coal mine in Kalimantan, completed in 2022 — shows what that looks like in practice, including the parts that are harder than the drawing set suggests.

Project Overview

  • Location: coal mine site, Kalimantan Island, Indonesia
  • Year: 2022
  • Capacity: 300-person camp, 294 beds
  • Product: quick-assembly container house (flat-pack system)
  • Quantity: 213 container units across 19 buildings
  • Shipping: 17 × 40HQ containers
  • Production: 15 days
  • Transport: 18 days
  • On-site installation: 30 days
  • Scope: staff dormitories, senior staff quarters, guest house, administration block, clinic, laundry, two canteens, warehouse and site inspection post. 


    What 213 Units Actually Built

    The camp is not one building repeated. It is a small settlement with its own services:

    • Junior staff dormitories: 10 blocks, 130 rooms, 260 beds — 13 rooms per block (7 × Type A + 6 × Type B), two beds per room, each with its own bathroom, plus one recreation room per block
    • Senior staff quarters: 2 blocks, 12 single rooms with private bathrooms
    • Guest house: 6 single rooms for the client and visitors
    • Administration dormitory: 8 rooms, 16 beds, with two shared bathrooms
    • Clinic: 4 rooms — consultation, pharmacy, first aid and ward, built to Indonesian camp compliance requirements
    • Laundry: 2 blocks, each split into dry and wet zones, four units in total
    • Canteens: 2 blocks, roughly 144 seats combined, each with multiple dining zones, a washing area and a serving room
    • Warehouse and inspection post: 14 standard units for site access control and storage

    Everything above was drawn, quoted and produced as one package, which is what makes a camp like this deliverable in a single mobilisation instead of a series of separate purchases.


    The Real Constraint Was Logistics, Not Manufacturing

    A remote mine site rarely accepts a container truck at the front gate. Material typically moves by sea to a regional port, then by road, then by whatever the last leg allows — and on this project the cargo changed hands more than once before it reached the site.

    Every transfer is a chance to lose or damage something. So the packing was treated as an engineering task, not a wrapping task: all materials were reinforced for repeated handling, with units bundled and marked by building so that the correct panels, doors, windows and fittings arrived together and could be unpacked against the drawings without sorting on the ground. On a site with no hardware store and no fabrication shop, a missing bracket is not an inconvenience — it is a stopped crew.

    Raised Bathrooms, Because the Ground Would Not Cooperate

    The change that mattered most on site was small. To make drainage and sewage pipe installation workable, the bathrooms were set on a raised platform rather than at floor level.

    That gave the installation team clear space underneath for pipe runs and connections, kept the wet areas clear of surface water and ground movement, and made future maintenance accessible without opening up a finished floor. It is the kind of detail that never appears in a brochure and decides whether a camp is commissioned on schedule.


    15 Days, 18 Days, 30 Days

    The schedule broke down into three clean blocks: 15 days of production in the factory, 18 days of transport, and 30 days of on-site installation with 9STATES technicians guiding the assembly.

    The point of that split is predictability. Site work was assembly and connection — positioning units, joining them, hooking up services that had already been tested in the factory — not construction from raw material. Thirty days of installation for 213 units across 19 buildings is a pace that only works when the components arrive finished, labelled and complete.

    Design Choices for a Tropical Mine Site

    • Independent bathrooms per room in the staff dormitories, rather than shared blocks, which removes a common source of camp friction
    • Corrosion-resistant finishes and sealed envelopes, suited to heavy rain and high humidity rather than the temperate assumptions most container systems are designed around
    • Ventilation and waterproofing detailed at the panel level, so performance does not depend on site workmanship
    • Standardised unit types (Type A, Type B, SS) that keep spare parts simple and let the client extend the camp later without a new design cycle




    Why This Project Matters

    Remote workforce accommodation is usually bought under time pressure, and time pressure is where conventional construction is weakest. Factory production removes weather from the critical path, and a properly engineered packing and transport plan removes the second-biggest risk — cargo that arrives incomplete.

    For clients planning camps in Indonesia, Kalimantan or comparable remote locations, the takeaway is that the building is the easy part. The delivery chain and the ground conditions are where a camp is won or lost, and both need to be designed in from the quotation stage, not discovered on site.

    9STATES MODULAR BUILDING SHANGHAI CO., LTD. has delivered workforce camps, site offices and modular accommodation across Southeast Asia, Africa, South America and the Middle East.

     
30,000㎡ of prefab housing and 40,000㎡ of material sheds built along the rail corridor for three construction sections. Delivered in phases, so later blocks were still on the production line while crews were already moving into the first ones.
The first station apartment project of "Ninghui" is located in Lishui District, Nanjing Airport Economic Demonstration Zone, which is a centralized medical quarantine and observation place to undertake inbound personnel at Lukou Airport port. The project adheres to the principle of "combination of peacetime and war".
Detachable container appartement for Shanghai workers' isolation dormitory
A 4-year repeat customer from Indonesia ordered 56 quick-assembly container dormitory units for their mining workers in East Kalimantan. Each unit (3×6×2.8m) features PVC flooring, rock wool insulated exterior walls, and EPS waterproof bathroom panels—tailored for tropical mining camp conditions.
9States successfully delivered 600 prefabricated container units for a large-scale Saudi labor camp project. Each unit measures 12×3.75m with enhanced ventilation corridors, raised roofs, reinforced sealing against sandstorms, and strengthened floor beams—tailored for extreme desert conditions.
Singapore containerHotel Apartment house nurse building. The project consists of 88units 3m*9m*2.8m(L*W*H) detacheabl container house, including walkways, asphalt tile roofs, fire panels, fire doors, aluminum Windows, and smart locks.The project has high requirements and high standards, and the materials have passed the Singapore COC certification. From raw material processing to installation completion, through the Singapore government acceptance, it has been completed successfully after more t

Gettingstarted is simple.Request a demo today.

FirstName*
LastName*
Email*
Company Name
Phone/Whatsapp*
Country/Region
File Upload
Message*